EXTENSION OF PROJECT SCHEDULE Updated 03/23/2017
- A written request for extension of the project implementation progress
-
Contents of the proposal:
- The progress of the project and fulfillment of financial obligation to the State since the issuance of the Certificate of investment registration or decision on investment policies up to the extension date;
- Explanation and length of extension;
- Plan for carrying on the project, including capital contribution plan, infrastructural development schedule, and inauguration schedule;
- The investor’s commitment to carry on the project.
-
Number of application sets: 01 original set
-
Time for processing project file: 15 working days
|
|