PROJECT SUSPENSION
Ngày cập nhật 23/03/2017

 

  • Application cases

The Management Committee shall decide to suspend part or all of the project in the following cases:

- For environmental recovery at the request of a environment authority;

- For implementation of occupational safety measures at the request of an labor authority;

- The project is suspended under the decision or judgment of the court or arbitral tribunal;

- The investor fails to adhere to the Certificate of investment registration and recommits administrative violations after incurring penalties.

  • Project file

- A written notice on the project suspension 

  •  Number of application sets: 01 original set
  • Time for processing project file: At once